Inland waterways
River and canal cargo delivery.
Electric cargo landing craft
Cargo capability. Shore-to-shore.
A 12-metre aluminium landing craft with twin CAMY electric outboards, a bow loading ramp and a 3-ton-class deck crane. Built around practical river, pier and approved island logistics.

01 / Vessel configuration
A compact cargo platform for destinations where fixed loading infrastructure is limited.

02 / Energy & performance
Updated brochure estimates: 13 kn light and 9 kn at the full 8-ton payload. Confirm performance through vessel trials.
Energy basis
80 kWAssumed combined battery draw at the 80% setting: 40 kWh/hour per motor.
| Range basis | Light · 13 kn | Loaded · 9 kn |
|---|---|---|
| Total · zero reserve | 120.4 | 83.3 |
| Return-trip radius · zero reserve | 60.2 | 41.7 |
| Total · 20% reserve | 96.3 | 66.7 |
| Return-trip radius · 20% reserve | 48.2 | 33.3 |
Theoretical estimates assume the stated speeds at 80 kW battery draw. Radius assumes equal out-and-back legs at the same loading. Auxiliary loads and unusable battery capacity are excluded; current, sea state and losses affect actual range. These are not guaranteed operating ranges.
03 / Weight & draft
Preliminary weight build-up and draft estimates from the latest five-page workboat brochure.
| Condition | Displacement | Estimated draft |
|---|---|---|
| Lightship | 8.5 t | 0.36–0.39 m |
| Maximum cargo | 16.5 t | 0.71–0.76 m |
| Recommended design condition* | 17.5–18.0 t | 0.75–0.83 m |
*Includes crew, EV auxiliaries, safety equipment, mooring gear and allowance. Design target: approximately 0.85 m loaded draft, leaving approximately 0.65 m of hull depth. Calculation basis: LWL 11.4 m, BWL 2.85 m, block coefficient 0.65–0.70, seawater. Freshwater draft is approximately 2.5% greater. Final hull lines, weight take-off, stability analysis, inclining test and authority/class approval are required.
04 / Service profile
River and canal cargo delivery.
Resort and approved coastal logistics.
Cargo transfer by ramp or crane.
Maintenance and project support.
Final service area, lifting limits and safety equipment remain subject to stability assessment, weather limitations, local operating conditions and authority or class approval. A 3-ton crane rating does not mean 3 tonnes can be lifted at every reach.
Our official partners
Electric power-system expertise and Thai shipyard capability, connected through BlueCurrent.